Crisis project: a robotic production line for electromobility
Situation
A fully automated production line for a Swiss group was severely delayed by missing expertise and weak project management. Seven-figure damages claims and a substantial loss of the end customer's trust were at stake.
Our contribution
Took over crisis project management on behalf of the holding company owner. Rapid familiarisation, rebuilding a specialist team, realistic scheduling, restoring the end customer's confidence and operational project leadership on site.
Results
- Trust rebuilt within three weeks
- Release and payment of an outstanding advance-payment invoice in the high six figures
- Successful preliminary acceptance after 3.5 months
- Seven-figure losses and damages claims avoided
- Delivery to the end customer with only a few weeks' delay and extension of the supply contract